Eco-Oil reported The Cartagena refinery has started a major maintenance process on three process unitshydrocracking, hydrogen and sulfur. These missions will last for about After 50 days, they reported.
(suggestion: Frontera signs agreement to import LPG at lowest cost via Cartagena)
Perform maintenanceo The company will invest $243 billion and will create approximately 1,500 direct jobs During the 50-day maintenance period.
this The Cartagena refinery has 35 units and processes 210,000 barrels of oil per day. According to Ecopetrol, the maintenance work will have no impact on the local liquid fuel supply.
(Respected: There are 600 MW of thermal power waiting for auction, but natural gas supply is needed)
“It is well known that major maintenance or plant shutdown is Inspect equipment to make necessary repairs, replace parts and perform technical measures or a process that allows the restoration or even improvement of the original functionality of the device” the company said.

cartagena refinery
Eco gasoline
During maintenancethree units will replace 1.2 million pounds of catalyst, According to the oil company, this is the largest change to the product to date.
(See also: Ecopetrol seeks to increase its commitment to U.S. fracking with new acquisition)
Likewise, in this process a Compressors, motors, pipes and
Switch,”To ensure safer and more efficient operations“.
In fact, Ecopetrol stressed that planning had taken more than two years to carry out these tasks, in order to ensure that the works could be completed within the scheduled 50 days.